CONSTRUCTION UPDATES

construction Progress

85.91%
*According to our internal inspection conducted on 31/05/2024, the overall project's progress is 85.91%.

31-05-2024

  1. Superstructure is completed.

  2. Block and Plaster works completed.

  3. Subsequent activities like MEP & Finishing works are in progress.

  4. Chillers received and installed at roof.

  5. Façade work is in progress and expected to complete by end of June.

  6. Elevator installation works completed.

  7. All Long Lead Items are delivered.

  8. Project development in progress.

  9. Project scheduled to be finished before time.

  10. All services connection process with authority started.

  11. Authority inspections will commence in July.

    Follow Us on: