CONSTRUCTION UPDATES

construction Progress

43.75%
*According to our internal inspection conducted on 31/05/2024, the overall project's progress is 43.75%.

31-05-2024

  1. Substructure is completed.

  2. Superstructure - 20th Floor completed.

  3. Block works 14th - 16th Floor in progress.

  4. Plaster works 8th-10th floor in progress.

  5. Façade works 1st - 6th Floor in progress.

  6. Subsequent activities like MEP & Finishing works are in progress in parallel to the structural work.