CONSTRUCTION UPDATES

construction Progress

35%
*According to our internal inspection conducted on 31/05/2024, the overall project's progress is 35%.

31-05-2024

  1. Substructure is completed.

  2. Superstructure - 20th floor in progress.

  3. Block works 13th - 15th floor in progress.

  4. Plaster works 7th - 9th floor in progress.

  5. Subsequent activities like MEP & Finishing works are in progress in parallel to the structural work.

  6. Project development in progress.

  7. DEWA Transformer payment done.