CONSTRUCTION UPDATES

construction Progress

Enabling Works in Progress

7%
*According to our internal inspection conducted on 31/05/2024, the overall project's progress is 7%.

31-05-2024

  1. Fencing work completed.

  2. Shoring Guide wall casting completed.

  3. Shoring Piles casting completed.

  4. Shoring works 100% completed.

  5. Piling works in progress.

  6. Soil shifting is in progress.

  7. Capping Beam casting is completed

  8. Dewatering system connection approved. Received authority approval.

  9. All Engineering submissions are in progress.

  10. Main contractor on board.

  11. Project is scheduled to be completed on time.

31-05-2024

  1. Guide Wall completed.

  2. Shoring works completed.

  3. Excavation works of Enabling contractor is completed.

  4. Enabling contractor handed over the site to Main Contractor.

  5. Main pile design submitted and approved by DM.

  6. Piling works in progress.

  7. Capping beam completed.

  8. Dewatering system approved and drilling of dewatering wells in progress.

  9. All Engineering submissions are in progress.

  10. Main contractor on board.

  11. Project is scheduled to be completed on time.